Sections

MW-02Progress Period : 2022-03-01 To 2022-03-31

  • Main Access Tunnel Excavation & Support (#1): completed
  • Main Access Tunnel Excavation & Support (#2):14.3 %
  • Surge Chamber Vault Access Tunnel: 97.7 %
  • Service Tunnel A: 99.5 %
  • Service Tunnel C: completed
  • Underground Powerhouse Excavation & Support: 8.6 %
  • Underground Transformer Cavern Excavation & Support: 8.5 %
  • Drain Tunnel: 94.5 %
  • GIS Room Access Tunnel: 98.9 %
  • Penstock Adit Tunnel No.01: 95.4 %
  • Penstock Adit Tunnel No.02: Completed


MW-01Progress Period : 2022-03-31 To 2022-03-31

Concrete Work Diversion Tunnels

Diversion Tunnel A

  • Inlet Structure 38 % completed.
  • Inlet Tunnel Linning 44 % completed.
  • Outlet Structure 24% completed.
  • Invert Levelling Concrete L/S 30% and R/S 26 % completed.

Diversion Tunnel B

  • Inlet Structure 53 % completed.
  • -Inlet Tunnel Linning 44 % completed.
  • -Outlet Structure 18% completed.
  • -Invert Levelling Concrete L/S 49% and R/S 66 % completed.
  • -Shear Zone Area 21% completed.

Left Bank Traffic Diversion Tunnel

  • -Underground Excavation Work 22% completed.


DASU KKH-01 : Relocation of Karakoram Highway Progress Period : 2022-03-01 To 2022-03-31

Progress of KKH-01 during March 2022

Contract Elapsed  Time Actual Progress Prior to this month Work Progress During this Month Total Progress (up to march 2022)
DASU KKH-01 Month (79.3) 153.4% 31.3% 0.17% 31.47%

The major activities undertaken during this month were:

  • After completion of excavation works for Uchar Nullah access road, Logro B tunnel outlet (Dasu direction) axillary works continued during the month.
  • Portal construction of K3 tunnel, back filling above outlet portal and Shotcrete at Inlet Portal continued during the month.
  • Excavation works at Zero point first and third benches continued during the month.
  • Breast wall construction works at K8 continued during the month under review.
  • Construction of retaining walls at K5, K6 and K7 continued during the month.


RAR-01 and RAR-02 ProgressProgress Period : 2022-03-01 To 2022-03-31

Progress on RAR-01 in the month of March-2022

Package

Elapsed time

Actual Work Progress Prior to this Month (%)

Work Progress of this Month

Work Progress up to this month

Month

%

Scheduled

%

Actual

%

Scheduled

%

Actual

%

ICB No. DASU-RAR-01

79.3

134.9

96.2

-

0.25

100

96.5

 

               

 

 

 

 

 

Major Activities of RAR-01

 The major activities undertaken during this month were:

 Construction Activities

  • · Side drain vertical portion concrete is in progress.
  • · Concrete edge protection barrier around K11+400 in completed.
  • · Concrete barrier at Siglo culvert right & left side in completed.
  • · Blasting & excavation work at local access at K11+600 in progress
  • · Fixing formwork for side drain around K11+200 and concrete for side drain wall.
  • · Fixing of wire mesh on edge barriers around K11+400 & completed.
  • · Concrete for side drain around K9+300 to K9+400 in progress and completed.
  • · Drilling for blasting around 0+250 in work progress at Komila bypass.
  • · Excavation work in progress around 0+750 at komila bypass.
  • · Excavation work in progress 0+950 at komila bypass.

Progress on RAR-02 in the month of March-2022

The progress of RAR-02 during this month is summarized in the following Table:

 

 

Package

Elapsed time

Actual Work Progress Prior to this Month (%)

Work Progress of this Month

Work Progress up to this month

Month

%

Scheduled

%

Actual

%

Scheduled

%

Actual

%

ICB No. DASU-RAR-02

10.4

43.4

0.8

4.40

0.15

33.7

0.9

 

 

 

 

 

 

 

The Contract has been commenced on 20th May 2021.

The progress of RAR-02 during this month is summarized in the following Table:

Major Activities of RAR-02

 The major construction activities undertaken during this month were:

  • · Blasting and mucking work for open excavation from K12+660 to K13+145 were conducted continuously.
  • · The Contractor has planned to mobilize to the Contractor's camp in Kaigah and he requested the Employer to arrange security. The Employer is processing the security arrangements, accordingly.
  • · The Contractor plan to start new work face in Kandia River, after the mobilization to the Kaigah camp.


Tl-01Progress Period : 2022-04-08 To 2022-05-08

Grid Station:

  • Control house building: Concrete of columns and trenchers, removal of Scaffolding/formwork from switch gear trench & columns.
  • Shifting of excavated material from terrace 1 to Dumping Area.
  • Shifting of back fill material from Alignment #1 to grid station.
  • Access Road: excavation on alignment #2.

AREA WISE PROGRESS OF TRANSMISSION LINE:

Area

Total Towers

Excavation

 

 

Slide Removal 

Foundation Concrete Completed

 Concrete   Backfilling

Completed

Soil Backfilling

Completed

Tower Erection Completed

Stringing spans

Completed

RoW

 

 

Comments

In Progress

Completed

Palas

      10

0

10

-

10

10

10

10

03

 

 

Pattan

98

0

90

-

87

60

82

84

13

08

Commencement of JKD towers still awaited.

Shek Band

23

0

23

-

23

23

23

23

17

0

 

Jalkot

20

0

20

-

20

07

20

20

15

0

 

TeyalMaidan

28

0

28

-

28

22

27

16

09

06

 

Total

179

0

170

0

168

122

162

151

57

14